Smart Solutions Case Studies

Shinn Mechanical Couples Milwaukee Tool and Victaulic to Go Extra Mile on Seattle Tunnel Project

Under pressure to make up for lost time on a huge tunneling project, Shinn Mechanical Inc. used cordless Milwaukee tools to install Victaulic grooved couplings on an innovative piping design, shaving months off the original schedule. “Pairing Victaulic couplings with Milwaukee tools allowed us to finish a job scheduled to take eight months in only 10 weeks,” said Mike Shinn, company founder.