Manufacturer: Lifting Gear Hire

Safety Tips for Maintaining Wire Ropes and Slings

Wire rope is a machine, and a rather complex machine. There are no precise rules to determine exactly when a wire rope sling has passed its service or expiration date. There are guidelines, though, to follow to know whether a sling is suitable for continued use or needs replacement.

Wire rope slings should be inspected prior to use to identify potential hazards or damage and to determine whether they are suitable for continued use. The Occupational Safety and Health Administration (OSHA) and ASME B30.9 standards dictate inspection intervals and procedures. They also require that inspections be executed by the sling user.

Basic Inspection Criteria

According to the Wire Rope Technical Board, proper inspection should follow a systemic procedure, as described in the Wire Rope Sling Users Manual:

  1. First, it is necessary that all parts of the sling are readily visible. The sling should be laid out so every part is accessible.
  2. Next, the sling should be sufficiently cleaned of dirt and grease so wires and fittings are easily seen. This can usually be accompanied with a wire brush or rags.
  3. The sling should then be given a thorough, systematic examination throughout its entire length, paying particular attention to sections showing the most wear.
  4. Special attention should also be paid to fittings and end attachments and areas of the sling adjacent to these fittings.
  5. When the worst section of a sling or the weakest link has been located, this area should then be carefully checked against the criteria.
  6. Label or identify slings that are inspected.
  7. Keep records of inspections that include dates and corresponding conditions of slings.
  8. Dispose immediately of slings that are rejected.

Ideally, other systems for ensuring the quality of your slings should be part of your warehouse or facility inspection procedures. For example, Lifting Gear Hire is completing the final stages of adopting a new, streamlined RFID tracking system to record when equipment was inspected, who inspected it, and if and when the equipment was damaged. You can also seek out good quality training resources or learning institutes that teach courses on how to properly inspect wire rope slings—preferably ones that also provide Rigging Gear Inspector certification.

Storage Procedures

A sling’s service life can be extended substantially with good care and maintenance. Proper storage demands that slings be housed in an environment where they are not exposed to water, extreme heat, corrosives, liquids, or sprays and not stored in a kinked position, among other things.

Slings should never be left beneath loads or lying around where they can be susceptible to damage. Steel is not impervious to destruction. Slings should be housed in a rack when not in use. Custom racks can be constructed to accommodate slings of any size.

As with most machines, wire rope is lubricated at the time of manufacture. No supplementary lubrication is generally required if the sling is used under typical conditions. However, if a sling is stored outside or in any environment that could cause corrosion, additional lubrication should be applied to prevent rusting or corrosion. If the wire rope needs to be lubricated, the same type of lubrication as used during manufacture should be applied.

The storage temperature plays an important role in preserving the lifespan of a sling. Generally, steel-cored slings should not be used at temperatures above 400° F or below –40° F. Although it is not always easy to see when a sling has been damaged, a general rule of thumb is that if there are any suspicions that a sling’s integrity may have been compromised, it should be taken out of service right away or, at the very least, the manufacturer should be consulted.

Safe Operating Temperatures

Follow the sling manufacturer’s recommendations regarding use of steel-cored wire rope slings of any grade at temperatures above 400° F or below –60° F. At these temperature extremes, the internal structure of the steel may start to realign. If a sling will be or has been used in extreme temperatures, consult the manufacturer about ways to prevent degradation.

Removal from Service

OSHA specifies that wire rope slings must be removed from service in any of the following conditions:

  • Ten randomly distributed broken wires in one rope lay or five broken wires in one strand in one rope lay.
  • Wear or scraping of one-third the original diameter of outside individual wires.
  • Kinking, crushing, bird-caging, or any other damage resulting in distortion of the wire rope structure.
  • Evidence of heat damage, seen as wire discoloration, burn marks, weld splatter, etc.
  • End attachments that are cracked, deformed, or worn.
  • Hooks that have been opened more than 15 percent of the normal throat opening, measured at the narrowest point, or twisted more than 10 degrees from the plane of the unbent hook.
  • Corrosion of the rope or end attachments. Only extreme corrosion is necessary to reject a sling. Light corrosion does not substantially affect the strength of a sling.

ASME B30.9 has similar standards as well as the following:

  • Bent hooks can be no more than 5 percent over the normal throat openings, measured at the narrowest point from the plane of the unbent hook.
  • Any evidence of eye splices that have slipped, tucked strands that have moved, or pressed sleeves that show serious damage may be sufficient cause to reject a sling.
  • A very common cause of damage is the kink which results from pulling through a loop while using a sling, thus causing wires and strands to be deformed and pushed out of their original position. This kink unbalances the sling, reducing its strength.

Should a sling be determined to be worn out or damaged beyond use, the inspector should immediately tag the sling as “do not use.” The sling should be destroyed as soon as possible by cutting the eye and fittings from the rope with a torch. Cutting the body of the sling is also appropriate. This method of destruction should deter another employee from mistakenly using a sling that has been retired from service. Any inspection program, however thorough, is of no value if the slings that have been rejected or retired are not disposed of properly.

Repairs

According to ASME B30.9, repairs should only be conducted by the manufacturer or a qualified individual with the appropriate experience and certifications. For example, if an end fitting such as a hook becomes bent beyond guidelines, it should be sent back to the manufacturer regardless of whether the wire rope sling is intact and undamaged.

All repairs conducted on wire rope slings will require some proof of restoration. Replacement parts should be the same as those used in the original manufacturing. Following repair, a proof test of structural integrity should be conducted. With wire rope slings, the proof test is a 200-percent load test.

Should the wire rope used to craft the sling itself become damaged, it should not be repaired under any circumstances. For example, if one of the wires is damaged by weld splatter or heat damage, it is not possible to remove the one strand of wire and replace it. It is also not necessarily cost-effective to do so, as repair costs may outweigh the value of the sling.

Conclusion

When and how often you should inspect a wire rope sling are often the subjects of debate. The number of inspections every year should correlate with the amount of usage. At a minimum, a wire rope sling should be inspected once a year. However, if it is used frequently or in conditions that may challenge the sling’s integrity, then it should be inspected every month or quarterly, at least.

You should keep written records of when the wire rope was last inspected in case an accident or other cause for concern occurs. Keeping records also prevents someone from sending out a wire rope sling that is unsafe or has not been inspected. After all, the most important thing on a jobsite is maintaining safety.

For more information about Lifting Gear Hire, visit lgh-usa.com.

Hayes Mechanical Employs Creative Solutions, Lifting Gear Hire Equipment to Meet Crucial Deadline

Success of Duct Replacement Project Prevents Power Plant Closure

Without careful planning and support from Lifting Gear Hire (LGH), Hayes Mechanical might not have been able to install the new ductwork required by the Environmental Protection Agency (EPA) for a Midwest power generation company, which would have caused the power plant to close. Thanks to high-quality LGH equipment, backed up by a strong commitment to customer service, Hayes Mechanical finished the project on time, and the unit was released back to the customer ahead of schedule.

Powerhouse Duct Conversion Faces Barriers

For the “hot to cold duct conversion” project, Hayes Mechanical installed new ductwork to reverse the flow of gases going through an existing electrostatic precipitator using air chain hoists, trolleys, MODULIFT® modular spreader beams, and rigging supplied by LGH. The project involved changing the flow of gases going through the precipitator to reduce the operating temperatures, which would in turn reduce mercury emissions. According to Bill Bluis, the vice president of industrial construction at Hayes Mechanical, the boiler flue gas duct modification project required the removal of over 625 linear feet of existing ductwork to be replaced with a new reconfigured design.

“With as many pieces as we needed, we knew we’d be getting the commitment and dedication that we needed for our equipment from Lifting Gear Hire.”

—Bill Bluis, Vice President of Industrial Construction, Hayes Mechanical

The existing precipitator structure was directly over the ductwork that required replacement, which prohibited the use of a heavy lift crane. Moreover, staying on schedule was paramount to the success of the project. The plant faced closure if the work was not completed and the EPA emission parameters were not met by the end of the year. These challenges also impacted the way the new ductwork would be built.

Equipment from LGH played a crucial role in Hayes Mechanical’s success installing new ductwork in a Midwest power plant in time to prevent the plant’s closure. Seventy-two duct modules complete with insulation and lagging were prefabricated, shipped by barge, then trucked the last few miles to the plant.
Equipment from LGH played a crucial role in Hayes Mechanical’s success installing new ductwork in a Midwest power plant in time to prevent the plant’s closure. Seventy-two duct modules complete with insulation and lagging were prefabricated, shipped by barge, then trucked the last few miles to the plant.

Bluis added, “This was an outdoor project, with the plant being located right on Lake Michigan, so weather was definitely a factor. Additionally, we were working around an operating facility with the second boiler on line during the course of the work.”

Design Is Key

The biggest key in implementing the project plan was developing concepts to perform the rigging and execution of the temporary rigging design so that Hayes Mechanical could work with the duct fabricator to manufacture 72 duct modules complete with insulation and lagging in certain sizes for the areas in which they were to be placed. The new duct modules were shipped by barge to the Waukegan Harbor and later trucked a few miles down to the plant.

Bob Segiet, project manager and site construction supervisor, said, “We had to design and install an extensive system of monorails, trolleys, and chainfalls to demo out over 400 tons of the old duct and to maneuver the new modularized sections back in.” Segiet continued, “When we talk about the monorail system, it wasn’t one point of entry and one end point. We erected 60 tons of temporary structural steel and used upwards of 70 individual rigging pieces like the chainfalls and trolleys to manipulate a few different locations at the same time in order to move the duct work in and out of the structure. It couldn’t be done one piece at a time. It would’ve taken too long.”

Quality, Customer Service Seal the Deal

Despite the challenges involved, it was clear to Bluis and Segiet just what was needed to ensure a successful project.

“We involved LGH’s local representative early on,” said Bluis. “We knew the quantities of the rigging we would be using were a little more than what they were used to seeing on a power plant job from us. We worked with the local rep to make sure we had the right pieces and quantities available right from the start of the job. Of course, there were other vendors available, but what sold it for us was obviously the quality of the equipment. With as many pieces as we needed, we knew we’d be getting the commitment and dedication that we needed for our equipment from LGH. Not to mention, if we had a piece of equipment go down, we’d get a spare or a replacement in less than 12 hours.”

“We have worked with LGH for many years,” Segiet added. “Because of the reliability and condition of the equipment, we were very confident that when the equipment came out, it was going to be rebuilt, inspected, and ready to go. Also, LGH provided all the documentation we needed for the lift plans as well. This made it very easy for us to get right into the project.

“There’s always potential for a piece to go down,” Segiet concluded. “When you’re using 46 chainfalls it’s a real possibility. However, LGH gave us spares, wrapped them in plastic, and told us if they’re not used, then return them and you will not be charged. That’s quality of service I’ve never seen before.”

From an engineering standpoint, the goal was to reduce the operating temperatures of the precipitator by 350° F. Thanks to the efforts exerted by Bluis’ and Segiet’s team, Hayes Mechanical was able to accomplish their endeavor, and the project was deemed a success. Reducing the operating temperatures of the precipitator lowered the mercury emissions present in the facility, allowing the facility to meet the EPA standards required and continue operation.

For more information, visit lgh-usa.com.

BMWC Safely Executes a Heavy Lift, Thanks to Lifting Gear Hire

Cooperation and Planning Help BMWC Move Quickly, Save Costs

For a challenging project with a short timeline, BMW Constructors, Inc. (BMWC), partnered with Lifting Gear Hire (LGH), who not only supplied the appropriately sized, tested, and certified lift equipment but also expertise in developing a lift plan. As a result, BWWC set two 15’ x 52’ cooling tower unit sections inside an active, working refinery without disrupting day-to-day operations, completing the project on schedule and under budget. In addition to coordinating placement and use of a 550-ton crane, submitting an engineer lift plan for approval, and preparing the site to meet the project soil compaction requirements, BMWC was also responsible for removing the HVAC/scrubber units.

The Lifting Solution

Lifting Gear Hire provided the correct design configuration of the rigging and modular spreader beams to the structural engineer to create the critical lift plan. The quoting process used by LGH assisted the structural engineers in easily identifying equipment weight and capacities needed for calculations, as well as providing all of the safety certifications needed. “The involvement of LGH’s team really built a high level of confidence with our client,” states Dan Stegvilas, BMWC purchasing manager. Stegvilas added, “LGH has also been proactive instead of reactive, and they are always available with the right tools and expertise when needed.”

The lift design configuration was planned so that the same rigging equipment could be used for both critical lifts in different configurations as needed, further enhancing BMWC’s cost- and time-savings. Modular spreader beams played a key role, allowing the project’s structural engineer to adjust the equipment according to each lift quickly—within the two-day time frame allotted for both lifts.

Ideal Outcome

The entire scope of work was completed in one week, with the critical lift taking place over a weekend. The project was completed without injury or incident, on schedule, and under budget as well. John Manta, BMWC vice president of marketing & sales, said, “Working with LGH is always a positive experience. From top to bottom within their organization, every individual that I’ve worked with or come across nationally has been 100-percent supportive of our company’s efforts in all areas.”

For more information, visit www.lgh-usa.com.

Popular Rental Equipment Can Meet Contractors’ Immediate Needs

The need for specialized equipment may arise so infrequently that a company cannot afford to purchase it. Moreover, storing, maintaining, and, in some cases, certifying equipment can create additional headaches. To meet their short-term needs, some contractors choose to rent equipment from sources such as Lifting Gear Hire Corporation (LGH). Some of the most popular rental equipment includes the following:

Modular spreader beams range in capacities from 24–1,000 tons and have spans ranging from 3’ to 100’. These beams are designed for one-man assembly. Most spreader beams can be manually handled onsite, reducing assembly time and the need for lifting equipment. They also have a variety of top and bottom rigging available.

Air chain hoists have capacities ranging from .5–50 tons. These hoists are designed for maximum strength-to-weight ratio. They function well in most working environments, use uncomplicated electronic controls, , and employ motors that function well in adverse working conditions. They can be chained to any height and can lift up to 50 times their own weight.

Come-a-longs are a versatile tool used for a variety of lifting or moving needs. They can be used in any angled position, even upside down. Come-a-longs are ideal for use in tight corners and have a capacity ranging from 0.75–9 tons. Come-a-longs are designed with low headroom and have a freewheeling capability that makes one-handed operation feasible. Because the braking mechanism is totally enclosed, the equipment is protected against dirt and moisture.

For more information, call 800-878- 7305, e-mail sales@lgh-usa.com, or visit www.lgh-usa.com.

12 Reasons to Rent vs. Buy Equipment

The question often arises within an organization, “For our next project, should we rent or should we buy equipment?” Renting equipment from companies like Lifting Gear Hire Corporation (LGH) comes with effective cost- and time-saving benefits. Keep these 12 reasons to rent in mind when organizing your next project.

Project Control

1. Reduced after-job disposal. What do you do with purchased equipment that is not needed after a job is complete? Do you keep it or sell it? What if it is broken and needs repair?

2. No obsolete equipment. When buying, you lock yourself into a long-term commitment. When you rent, you get the equipment you need only for as long as you need it.

3. Accurate cost control. Renting equipment allows you to determine costs easily and accurately for your project.

Productivity on the Job

4. Right tool for the job. By renting equipment, you can rent the exact piece and quantity needed.

5. Well-maintained and ready to use. Equipment operating conditions can be severe, so equipment must be tough to survive and perform well. Renting equipment from reputable outlets like LGH guarantees you’ll receive equipment that is durable, certified, and ready for safe use.

6. No breakdown problems. Equipment comes serviced and ready to use. LGH carries branded equipment tested to ANSI standards.

Inventory Management

7. Minimal equipment required. Get the exact equipment needed for the job. Eliminate possible problems or extra expenses that may come from managing equipment inventory.

8. No storage costs. Renting equipment eliminates the need to store equipment after job completion. Rented equipment is delivered when and where you need it and retrieved immediately after use.

9. Reduced maintenance expense. Renting equipment eliminates the need for service and certification because it is taken care of for you.

Corporate Benefits

10. Reduced property tax. Did you know that property taxes are reduced on rented equipment? Renting your next set of equipment can help reduce expenses.

11. Increased borrowing capacity. Renting equipment instead of purchasing can be a convenient and easy process.

12. Conservation of capital. Renting equipment can help you conserve capital by avoiding the need to spend additional money on equipment that may not be used again.

Renting equipment can be beneficial for your organization. For your next project, keep these 12 reasons to rent in mind to save time and money.

For more information, visit www.lgh-usa.com or call 800-878-7305.

MCAA welcomes Lifting Gear Hire Corporation as a new member.