Major Growth Expected for Prefabrication and Modular Construction, New Study Finds

January 29, 2020

Findings of a landmark Dodge Data & Analytics study on the use of fabrication and modular construction show that most design and construction professionals using these methods experience improved productivity and project quality, plus increases in schedule certainty. MCAA partnered with Dodge to produce the report, which includes input from many MCAA members.

The Prefabrication and Modular Construction SmartMarket Report based on the study’s findings provides a comprehensive examination of the current state and future expectations for prefabrication and modular construction. It takes a close look at critical drivers, obstacles and benefits of using these methods, based on insight from architects, engineers and contractors already leveraging them.

The report shows that architects, engineers and contractors that have used these methods plan to significantly increase their engagement with them, especially for healthcare facilities, hotels and motels, multifamily projects, and college buildings and dormitories, which are at the vanguard of the new wave of interest in these methods. Critical trends in the construction industry, such as shorter project schedules and workforce shortages, are driving wider use of these methods, and technology like building information modeling (BIM) is enabling increased use.

In order to better understand the critical drivers and obstacles for using these methods and the benefits achieved, the study focuses on the architects, engineers and contractors that are already using them.

When it comes to methods already in use, the study shows that:

  • Prefabricating single-trade assemblies (such as plumbing assemblies behind the wall in hospital rooms) is widely practiced, with 62% of respondents using prefabricated single-trade assemblies in the last three years.
  • 48% of those doing modular are using panelized modular components (such as wall or floor panels).
  • Use of each of these methods is expected to increase in the next three years, with the percentage of those leveraging them on 10% or more of their projects nearly 15 points higher than present use.

However, most interesting growth is expected in practices less widely used now:

  • Prefabricated multi-trade assemblies, which involve the work of several trades combined together (such as a corridor rack in a hospital) will be used by 58% of those doing prefabrication in general—up dramatically from the 33% using this approach now.
  • Equally dramatic growth is seen among those doing modular construction in the use of full volumetric approach, in which entire parts of buildings (such as bathrooms or hotel and hospital rooms) are delivered preconstructed onsite and assembled together. A striking 61% expect to employ that method at least 10% of their projects in the next three years, up from just 44% of those doing modular construction who report using this method currently.

“It comes as no surprise to us that more developers and GCs plan to use modular construction over the next few years,” said Tom Hardiman, Executive Director of the Modular Building Institute. “The lack of adequate housing and the shortage of skilled labor, coupled with chronic cost and schedule overruns are leading more people towards this process.”

And when it comes to benefits of use:

  • About 90% report that they achieve improved productivity, improved quality and increased schedule certainty when using these methods compared to traditional stick-built construction.
  • 80% or more also report that they see improved cost predictability, reduced waste and increased client satisfaction.
  • Improved schedule performance, decreased construction costs and improved quality are also the top drivers for increasing their use of prefabrication and modular construction in the next three years.

The use of building information modeling (BIM) is also tied to the experience of those benefits. Among those using BIM on the majority of their projects, 60% credit it with improving the schedule performance of their prefabricated or modular projects, and 50% with improving budget performance. “BIM improves the prefabrication and modular process by providing the means to accelerate the design early enough to take advantage of these approaches and then offering certainty during the entire process,” says Steve Jones, senior director of industry insights at Dodge Data and Analytics. “Having these tools helps enable the industry to invest more in the use of multi-trade assemblies and volumetric construction in particular and may be contributing to the strong growth expected in these areas.”

The greatest growth in the use of these methods will be in building types in which they are already well established, such as healthcare facilities, hotels and motels, multifamily and college buildings and dormitories. However, a sizable percentage also expect low-rise offices, K-12 schools, public buildings and commercial warehouse to experience a high frequency of use of prefabrication or modular construction.

The report findings will be discussed during a general session at the MCAA Technology Conference.

DOWNLOAD
Related Articles
A new Dodge Data & Analytics study on mechanical and HVAC contractors using BIM shows that most mechanical contractors that use BIM experience benefits such as improved cost and schedule performance, lower labor costs and greater productivity. MCAA partnered with Dodge to produce the report, which includes input from many MCAA members.…
Every year, the MCAA Technology Conference brings ideas and innovation to MCAA members. This year’s event was no exception. Take a look, and plan to join us next year. MCAA thanks our title sponsor, Trimble, and our event sponsors: Autodesk, DEWALT and Rhumbix.…
MCAA is partnering with Dodge Data & Analytics to study the value of BIM for mechanical construction, HVAC, and plumbing contractors. This is the first of a larger, ongoing series of BIM studies to focus specifically on our industry. It will shed light on the opportunities and challenges of using BIM and VDC for your work. Your participation is vital to the study’s success, even if you have no experience with BIM.…
MCAA’s Virtual Trade Show connects our contractor members with the members of MCAA’s Manufacturer/Supplier Council.…

Thank you @ufcw135 for using a union signatory contractor AO Reed and qualified union service plumber Peggy Bearden! #unionplumber #plumbingservice #aoreed #unionproud #uaproud #unionsignatory #aoreed

Another great example of modular construction - Corrigan & Company built 296 bathroom modules offsite for St. Louis University/SSM Replacement Hospital. Coordinated multiple trades and had them pre-inspected before they left the shop.

Load More...