Southland Industries Uses Integrated Project Delivery to Speed Delivery of COVID-19 Facility

June 3, 2020

Southland Industries and the Integrated Project Delivery (IPD) team at Penn Medicine shaved 15 months from the construction schedule for a portion of a new hospital tower in University City, Pennsylvania, to prepare for the potential influx of COVID-19 patients.

Operationalizing the newly-constructed Pavilion took the team two weeks to bring 120 patient rooms and associated support spaces online. Southland installed a temporary med-vac system, medical gas piping, electric water heaters, medical air manifolds, hot water heaters, temporary plumbing fixtures, and temporary piping and ductwork.

Jim Meacham, Southland’s Mid-Atlantic Division Leader, explained that Southland teams were able to tackle the challenge of accelerating such a critical project through an IPD approach, clear and consistent communication, the willingness to step up, and dividing up the workload between engineers, project teams, and superintendents.

“The IFOA IPD contract method allowed for immediate collaboration amongst all the IPD partners to develop the right design solution to temporarily activate the hospital, with realistic jobsite condition awareness followed by instant decision making,” said Meacham. “Co-location and the collaboration developed early on during the formation stages of this project really paid off with the ability to expedite a solution that met Penn’s and the city’s needs.”

The facility was recently connected to the existing hospital of the University of Pennsylvania (HUP) via a tunnel, which creates a pathway for hospital staff to bring low-risk non-COVID patients over from the existing hospital. Moving the patients prevents existing cases from being exposed to new COVID-19 admissions.

Jim Meacham says, “we are faced with a real crisis and the majority of the state has suffered restrictions and closures. The PennFIRST team did an amazing job bringing this facility on line in the time required. The high level of confidence amongst the entire project team resulted in complete and timely execution, where everyone acted very quickly and decisively, while outlining and tracking each level of detail and associated sequencing required.”

Southland Industries continues to collaborate on COVID-19 facilities. They contributed to the surge facility project at the Walter E. Washington Convention Center that was facilitated in just over three weeks. We are all in this together.

Related Articles
MCAA hosted its first Field Leaders Conference of 2025 from May 12-14 in Washington, DC. With over 140 registrants, the event provided an engaging and impactful experience for emerging leaders in the mechanical contracting industry. MCAA’s next Field Leaders Conference will take place in Toronto, ON from September 15-17. Registration will open May 27, 2025.…
MCAA’s Virtual Trade Show connects our contractor members with the members of MCAA’s Manufacturer/Supplier Council.…
By swapping out Excel spreadsheets for MSUITE software across multiple fabrication shops, McCarl’s Industrial and Mechanical Contractors now has real-time visibility into their workflow, not the two-to-three-day lag time. Adopting a fully digital platform has optimized workflows and increased operational efficiency.…
Bruno is a Mechanical Engineering student at Fairleigh Dickinson University and graduating in May.  He is an active member of his student chapter, served as President, Vice President, and Recruitment Chair, and interned at MCAA Member, Mid-Atlantic Mechanical.  Post-graduation, Bruno will be continuing on at Mid-Atlantic as a full-time Project Engineer.…
Load More...