Murray Company Installs First-of-its-Kind Plumbing Systems in Southern California for the Santa Monica City Hall Building

July 16, 2020

MCAA member companies continue to collaborate on current projects, finding and creating innovative techniques and solutions. Read below to learn more about CPMCA member Murray Company’s work on the Santa Monica City Hall Building.

Murray Company was brought on by general contractor Hathaway Dinwiddie to install Southern California’s first-of-its-kind fully functioning plumbing system that complies with the Living Building Challenge (LBC) requirements set forth by the International Living Future Institute.

The project is a 50,000-square-foot building attached to a registered historic landmark, the Santa Monica City Hall Building. The building, located in Santa Monica, Calif., will house the City Building & Safety Permit Services Center, in addition to City staff offices and ancillary spaces currently housed in multiple leased spaces throughout the city.

The City is pursuing a full LBC certification which provides the most sustainable design, construction, and operation of the facility. The LBC is the most stringent sustainability standard for the construction industry. It focuses on 20 imperatives, including energy, water, construction waste and urban agriculture. Regenerative power will use the natural environment to bring this unique building to life. 

The building façade is heavily fritted to minimize heat gain and energy solutions like PhaseChange, an organic material found in the walls designed to melt and absorb heat in its space.  This heat absorption prevents high temperatures from entering the building, creating a thermal mass barrier. These are just some of the ways the building attains its Net Zero and sustainability goals.

This 3-story, above-grade concrete structure (plus a basement) includes mechanically operated glazing vents, photovoltaics, gray water treatment for irrigation demand, and rainwater treatment for potable water use within the building. The Murray Company team installed a 40,000 gallon underground rainwater collection tank (measuring 10 feet x 74 feet) that collects rooftop rainwater from the storm and overflow drains as well as the carport canopies adjacent to the building.  The rainwater distribution piping used for this application is 316 stainless steel with Shurjoint couplings that have an internal gasket rated for potable water use (EPDM-w).

Additionally, the site includes a chemical injection water treatment system called On-Site Hypochlorite Generation (OSHG) system, manufactured by PSI Water Technologies, Inc.  This allows the potable water system to be dosed with chlorination and fluoride that will be integrated into the potable water distribution system throughout the facility. 

Another unique feature is the 100 percent waste conversion to compost system, which ties in a foam flush toilet system to expend only 3 tablespoons of water per flush. Six compost bins were key to the water strategy, providing a 50 percent reduction in the need for potable water demand.

Murray Company’s crew included team captain Steve Molina (Project Manager) alongside Virginia Brown (Project Executive), Aina Cortez (Project Engineer), Jason Hernandez (General Superintendent), Gerald Bender (Detailer) and Mike Bogroff (Foreman). The team’s innovation and adaptability to the demands of this extraordinary project are the new way forward for plumbing and construction.

Related Articles
Welcome to Inside MCAA, The Blueprint to Mechanical Contracting, the podcast dedicated to unveiling the strategies and resources that power success within the Mechanical Contractors Association of America. Hosted by renowned Customer Experience Coach and NEI Instructor Frank Favaro, each episode dives deep into the wealth of educational tools, networking opportunities, and advocacy efforts that define MCAA.…
Registration is now open for two impactful labor relations events taking place consecutively in Las Vegas this October—designed to strengthen negotiation skills, improve labor-management collaboration, and advance our industry together. The back-to-back MCAA Collective Bargaining Conference and UA/MCAA Labor Relations Conference offer a unique opportunity to develop aligned strategies, share perspectives, and build stronger labor-management relationships across the mechanical industry.…
Each year, thousands of workers suffer from heat illness while working in high temperatures, direct sun, and humid conditions; dozens even die. MCAA's Heat Stress resources, alongside those from our partners at OSHA, CNA, and MILWAUKEE TOOL, provide strategies and tips for protecting those workers. These are just a few of MCAA’s educational resources that are free to MCAA members as a benefit of membership.…
Mark your calendars for the 2025 MSCA Education Conference, November 9–12 at the Fairmont Scottsdale Princess. This year’s theme, Transform, challenges us to rethink how we inspire teams within our organizations while still being leaders and advancing the industry. In addition to our in-depth education sessions and conference-favorite peer-to-peer discussion roundtables, we have a great line up of keynote speakers. Registration opens June 18th.…
Load More...