Smith & Oby Combines Prefabrication and ERICO’s New CADDY ROD LOCK System to Cut Installation Time
In early 2011, Smith & Oby Company began work on a new office building in Cleveland, OH, that included 250 active chilled beams, which required an extensive amount of small-diameter copper pipe and multiple trapeze racking systems. To manage installation of approximately 28,000 linear feet of pipe in a 95,000-square-foot building, Smith & Oby turned to ERICO for an innovative and time-saving installation solution.