Palmer Christiansen Cuts Costs, Installation Time with Victaulic Grooved Products, Keeping Salt Lake City Courthouse on Schedule

With 24 months to install 130,800’ of pipe, Palmer Christiansen Company relied on Victaulic for high-quality systems that reduce labor costs and installation time. As a result, the new federal courthousein Salt Lake City, UT, is expected to open in March 2014, with the mechanical system coming in on budget and ahead of schedule.