Smart Solutions

Spaeder Saves Weeks on Layout with DEWALT HangerWorks

The heat map feature in DEWALT’s HangerWorks, shown here, was perfect for communicating the areas of impact to the slab loads resulting from the coordination process, ultimately saving Spaeder weeks of time in hanger layout.

To meet an engineer’s demanding criteria for embedding hanger assemblies into concrete slabs for a new seven-story building, Wm. T. Spaeder Company used DEWALT HangerWorks™ software, not only achieving the difficult task but saving weeks of layout time as well. HangerWorks also improved the prefabrication process by enhancing labeling and reporting in Spaeder’s building information modeling (BIM) program.

Jonathan Marsh, chief technology officer and division manager of virtual design and construction at Spaeder, based in Erie, PA, was so pleased with the outcome, he posted his thoughts on LinkedIn. “The craziest hanger load on slab validation we have ever done,” wrote Marsh. “A big thank you to DEWALT HangerWorks for saving us weeks!”

Extra Caution, Extra Headaches

Because of an experience with structural failure caused by overloaded slabs, the engineer for this project was determined to be particularly cautious about the loads added to the slabs as the mechanical and electrical systems were coordinated for the building. At first, the engineer wanted to avoid any attachments to the slab.

After discussion with the construction management team, the engineer gave Spaeder an alternative. They would be permitted to hang from the slab as long as they used concrete embeds prior to the pour and could demonstrate to the engineer’s satisfaction that they had met specific criteria.

The engineering criteria were not as simple as circles or squares surrounding each embed location. The criteria represented accumulative loads for a section of concrete 2’ wide and extending from one beam to another at every hanger location. The engineer gave Spaeder maximum weights for areas of overlap and even specific criteria based on distance from beams.

These demands could have posed a giant engineering nightmare, because the building needed approximately 25,000 hangers embedded in the slab. In fact, the criteria were so complex they required three pages of explanation. The challenge was presented to three separate subcontracting companies, who also needed to find a way to come together and work out the best available slab loads to accommodate all the building systems. Finally, all of this coordination, design, and planning had to happen fast. Construction of the building had begun, and anything in the slab had to have an embed installed prior to pouring concrete.

Handled with HangerWorks

DEWALT’s HangerWorks software is a plug-in for Autodesk Revit™ that automates the placement and design of hangers and seismic bracing for mechanical, electrical, and plumbing (MEP) systems. Complex engineering calculations are built in to the tool that enable it to size hanger assemblies based  on the weights of the MEP system, including contents (e.g., water, wire, or air), and determine hanger locations based on building code requirements and user-defined project standards. With HangerWorks, Spaeder tackled two critical problems.

First, HangerWorks allowed Spaeder to make basic point load calculations for loads that were not static. Given the involvement of multiple subcontractors, the team needed to balance all of the systems’ weights to avoid overloading any areas of the slab. With real-time reporting of loads, Spaeder could easily and quickly relocate hangers to redistribute loads to areas of the slab with available
capacity.

Spaeder modified the heat map using HangerWorks, attached it to the various hanger rods throughout their model, then gathered load data to demonstrate to the engineer that all the criteria had been met.

Second, HangerWorks succeeded in communicating the slab loads graphically in a way that everyone could understand and that alleviated the engineer’s concerns. The heat map feature in HangerWorks proved to be the perfect tool to communicate the areas of impact to the slab loads resulting from the coordination process. While the criteria given to Spaeder by the engineer were too complex to allow for use of the out-of-the-box heat map, Spaeder used HangerWorks to create a modified heat map, which they attached to the various hanger rods throughout their model. Those rods then provided individual load reports, allowing Spaeder to successfully demonstrate to the engineer that all the criteria had been met.

Moreover, the HangerWorks heat map provided a guide to enable the building owner to make good decisions about future installations within the building. “Upon creation of our first heat map and presentation to the engineer, Spaeder received applause from the owner’s representatives and members of the design and coordination team for having met the challenge and been able to pull together a workable solution,” said Marsh.

Prefab Pays Off

Had DEWALT HangerWorks served only to provide engineering calculations, it would have been well worth Spaeder’s investment, Marsh observed. HangerWorks also delivered on the prefabrication side, enabling Spaeder to automate their BIM of materials, hanger spool sheet, and prefabrication labels. By quickly modifying their existing hanger fabrication workflows to work in conjunction with HangerWorks, Spaeder leveraged the software’s enhanced reporting functions to produce better labels, improved fabrication drawings, and more useful field installation drawings. The drawings included information vital to the foreman’s understanding of the installation process and helped with sizing of strut channel and other secondary support materials. In addition, Spaeder ended up being paid to lay out fire protection and sheet metal anchors, as they were already controlling the hangers for all the trades on the project.

For more information, visit anchors.dewalt.com/anchors.